3mar04 Proposed data sets delivered to J. McMullin
3mar-19may
Data pre-testing and verification that the data is
appropriate for TST2 goals.
19may D. Shepherd delivers detailed Test Plan and proposed time-line
to J. McMullin
19may-16jul
Development and pre-testing as needed
19-30jul Intensive testing by D. Shepherd, software team, and NAUG
members
30jul First round of internal testing complete (at least 2 people
have reduced each dataset and delivered images & scripts).
Cookbook delivered to D. Shepherd
4aug D. Shepherd verifies cookbook (text and scripts) and
spot checks User Reference Manual and supporting
mosaic help documentation.
Cookbook development deferred to End of August.
15aug D. Shepherd provides testers with status update for the test.
D. Shepherd provides questionnaire and requirements spread
sheets to J. McMullin to put on the TST2 web page.
15aug SS 7.5 (to be used for TST2); solicit information on OSs, media
15sep NAUG/Internal testing;Cookbook development
-15oct Last minute bug fixes and documentation updates.
15-22oct Final verification of data reduction paths, documentation,
web site.
22oct D. Shepherd and B. Glendenning give go-ahead for test start
assuming all criteria have been met.
Distribution of data/software
25oct Testers receive memo from D. Shepherd giving final details of
the test.
Test Starts (on a Wednesday)
25oct-25nov
Support testers as needed.
25nov Test Ends (Friday)
All testers deliver scripts, images, questionnaires, graded
requirements to D. Shepherd.
15dec D. Shepherd delivers final report to J. McMullin and ALMA
management.
-----------------
History
03mar04 - NGC 4826 and NGC 1333, Source IRS 2a datasets chosen and
delivered to Joe McMullin for verification
19may04 - Test plan first draft delivered to J. McMullin &
B. Glendenning
20jul04 - Delay TST2 to September 15th
01sep04 - Delay TST1.1 (renamed from TST2) to October 22