3mar04   Proposed data sets delivered to J. McMullin 
3mar-19may 
         Data pre-testing and verification that the data is
         appropriate for TST2 goals.  
19may    D. Shepherd delivers detailed Test Plan and proposed time-line 
         to J. McMullin
19may-16jul 
         Development and pre-testing as needed
19-30jul Intensive testing by D. Shepherd, software team, and NAUG 
         members 
30jul    First round of internal testing complete (at least 2 people
         have reduced each dataset and delivered images & scripts).  
         Cookbook delivered to D. Shepherd
4aug     D. Shepherd verifies cookbook (text and scripts) and 
         spot checks User Reference Manual and supporting
         mosaic help documentation.
	 Cookbook development deferred to End of August.
15aug     D. Shepherd provides testers with status update for the test.  
         D. Shepherd provides questionnaire and requirements spread
         sheets to J. McMullin to put on the TST2 web page.  
15aug    SS 7.5 (to be used for TST2); solicit information on OSs, media
15sep    NAUG/Internal testing;Cookbook development
-15oct   Last minute bug fixes and documentation updates. 
15-22oct Final verification of data reduction paths, documentation, 
         web site.  
22oct    D. Shepherd and B. Glendenning give go-ahead for test start 
         assuming all criteria have been met.  
	 Distribution of data/software
25oct    Testers receive memo from D. Shepherd giving final details of
         the test.  
         Test Starts (on a Wednesday)
25oct-25nov
         Support testers as needed.  
25nov    Test Ends (Friday)
         All testers deliver scripts, images, questionnaires, graded
         requirements to D. Shepherd.  
15dec    D. Shepherd delivers final report to J. McMullin and ALMA
         management.  
         

-----------------

History

03mar04 - NGC 4826 and NGC 1333, Source IRS 2a datasets chosen and 
          delivered to Joe McMullin for verification 
19may04 - Test plan first draft delivered to J. McMullin & 
          B. Glendenning
20jul04	- Delay TST2 to September 15th
01sep04  - Delay TST1.1 (renamed from TST2) to October 22